Dec
28

micropiles to 4th storey apartment -completed 65 point



laying sand to sub-base

laying crusher run to Base

kentledge main beam failure

>> 
Dec
26

Load Test to 300 dia micropile at block aprtment 5th storey






OFFICE BLOCK -GROUND BEAM IN PROGRESS

>> 
Dec
22

>> 
Dec
15

OUTLET POND (no.1)






LOADTEST TO MICRO PILE:-) MLT (maintain load test)
4th Storey -pile dia. 300mm
Approximate Total Hours---> 50 HOURS 2 Cycle (Anchor Type)
Max.Test Load-1350 kn(200%WL) 7200.00(Psi)
Started 1700 hrs Sunday 13th-End 1900 hrs Tuesday 15th


Office Block 8 Dec 2009

>> 
Dec
09





CLICK THIS TO ENLARGE OFFICE BLOCK 10 DEC
more view on office block CLICK

CLICK THIS TO ENLARGE POND no 1 OUTLET STRUCTURE 10 DEC

CLICK THIS TO ENLARGE
QUARTERS BLOCK 10DEC needs more view move your mouse cursor here LEFT CLICK ONCE

Kemajuan 01/02 Disember 2009

>> 
Dec
02

OFFICE BLOCK
PAD FOOTING WORK IN PROGRESSACTIVITY ON QUARTERS 5TH STOREY
MICRO PILES WORK
01 DEC 2009
INSERT REBARGROUT MIXER
GROUTING WORKMICRO PILE QUARTERS 4TH STOREYS
02 DEC 2009